Construction Loan Mistakes to Avoid When Building in NSW

Learn how NSW building rules shape your progress payments, deposit and drawdowns, so your build loan does not stall halfway.

Hero Image for Construction Loan Mistakes to Avoid When Building in NSW

If you are building in Merrylands, your construction loan is shaped by NSW building law as much as by your lender. Get the contract and payment schedule wrong, and the loan can stall before the roof goes on.

There is no separate law for a construction loan as a product. It sits under general credit and lending rules, while the payments it funds follow the state's home building laws. Here is what that means for your build.

What Rules Apply to a Construction Loan in NSW?

A construction loan is covered by general lending and credit rules, and your builder's payments are controlled by the Home Building Act 1989 (NSW). Your lender then sets its own terms on top, such as the number of drawdowns, inspections, fees and the rate.

This means two sets of rules must line up. The contract decides when your builder can ask for money. The lender decides when it will release money. A mismatch between the two is where builds get delayed.

Deposit Limits and Progress Payments Under the Home Building Act

In NSW, the maximum deposit on a home building contract is 10 per cent, and work over $20,000 needs a large job contract that includes a progress payment schedule. Progress payments must match the work actually carried out.

Payments can be fixed amounts or percentages after set stages, amounts claimed as work is done and costs are incurred with supporting documents, or a mix of both. The contract also comes with a cooling-off period of five clear business days.

The trade-off is that a tight schedule protects you from paying ahead of the work, but it also means you need your funds lined up for each stage. Your construction loan should be set up so each claim can be paid when it falls due.

Do Not Pay Before Home Building Compensation Cover Is in Place

For contracts over $20,000, your builder cannot ask for a deposit or any other payment until Home Building Compensation Scheme cover is taken out and you have been given the certificate. If a builder asks for money first, pause and ask for the certificate.

This matters for your lender too, because paying early or paying for work not yet done can leave you out of pocket if the builder fails to finish.

Ready to get started?

Book a chat with a Finance & Mortgage Broker at Credible Finance today.

When Does Repayment Start on a Construction Loan?

NSW Government guidance says a borrower financing a project home must start mortgage repayments once the first progress payment is made and they begin to draw down on the loan. Check with your lender about any special requirements for progress payments.

Interest is commonly calculated on the drawn balance, but this varies by lender. Check your lender's product terms. If interest is charged on the drawn balance, repayments rise as the build moves along, so you need to plan for the final stage, when most of the loan is drawn. Whether the loan is interest-only during the build is set by your lender.

Illustrative Example: Drawdown Costs at 6.75% p.a.

Using an illustrative rate of 6.75% p.a., interest on a drawn balance of $200,000 is about $13,500 a year, or roughly $1,125 a month if the loan is interest-only. This is not a quote, and your actual rate depends on your lender and deposit.

Consider a Merrylands couple building a home on land they already own. Their loan is $600,000 in total. Assume interest is charged on the drawn balance. At the slab stage, only $120,000 has been drawn, so interest at the example rate is about $8,100 a year, or $675 a month. By the final stage, the full $600,000 is drawn, and interest alone rises to about $40,500 a year, or $3,375 a month.

The couple use a borrowing capacity check before signing, and set aside a buffer for the later months. The outcome is that the final stage payments do not come as a surprise, and they keep their budget steady through handover. The trade-off is that holding extra savings in a buffer means less money working elsewhere.

How Lenders Assess You During a Build

Lenders must assess whether you can meet repayments at a rate at least 3 percentage points above the loan rate. This buffer was confirmed by APRA on 28 May 2026.

Finance for building new dwellings is exempt from APRA's debt-to-income limit, which restricts how much of a lender's new lending can be at six times income or more. That exemption does not remove the serviceability test, so your income still has to support the loan.

Bonuses and overtime are often discounted by lenders, so a stable base income helps your application.

Progress Inspections and What They Cost

Building Commission NSW gives $250 to $500 as an indicative cost of each progress inspection by an inspector who is not connected to the builder. Lender inspection and evidence requirements vary. Ask your lender what it requires before each drawdown.

If the schedule has five stages, that could add a modest cost over the build. The benefit is that you only release funds for work that has been done.

First Home Owner Grant When You Build in NSW

The NSW First Home Owner Grant is $10,000. For vacant land with a comprehensive home building contract, the combined value of land, contract and any variations must not exceed $750,000.

Applications needed for settlement or a first drawdown or progress payment go through the approved agent providing the finance. Otherwise, you lodge within 12 months of settlement or completed construction. The home must be your principal place of residence for at least 12 continuous months, starting within 12 months of completion. If you are a first-timer, our first home buyers page explains more.

Building an Investment Property: Tax Points to Raise With Your Accountant

The ATO says interest on a construction loan can be claimed on a rental build, while interest on a separate loan used for the vacant land cannot be claimed while the land remains vacant. If one loan funds both, the interest must be apportioned.

Capital works deductions on a residential building generally start only once construction is completed. The rules are changing for some investors from 1 July 2027, and the Australian Government says new builds can continue to be negatively geared. Speak to your accountant about how this applies to your situation, as outcomes depend on your circumstances. Our investment loans page covers the lending side.

A Common Mistake: Treating the Loan Like a Standard Home Loan

The most common mistake is setting up a build loan like a standard home loan, without checking the payment schedule in your contract against the lender's drawdown rules. Get both documents in front of a broker before you sign the building contract, not after.

We compare options from lenders across Australia, and the right match depends on your build type, deposit and income.

Call one of our team or book an appointment at a time that works for you, and we will check your contract against your loan before you commit.

Frequently Asked Questions

What is the maximum deposit on a building contract in NSW?

Under the Home Building Act 1989 (NSW), the maximum deposit is 10 per cent. Work over $20,000 also needs a large job contract with a progress payment schedule.

When do repayments start on a construction loan?

NSW Government guidance says repayments start once the first progress payment is made and you begin to draw down. Your lender sets the specific terms.

Do I pay interest on the full construction loan from day one?

Interest is commonly calculated on the drawn balance, but this varies by lender. Check your lender's product terms.

How much does a progress inspection cost in NSW?

Building Commission NSW gives $250 to $500 as an indicative cost of each progress inspection. Lender inspection requirements vary, so ask your lender what it requires before each drawdown.